Skip to content

Solar Regulations & Incentives in Nigeria

The Electricity Act 2023 lets states regulate their own electricity markets. NERC issued new Mini-Grid Regulations in April 2026 and Net Billing Regulations in June 2026 for grid-connected systems of…

The Electricity Act 2023 lets states regulate their own electricity markets. NERC issued new Mini-Grid Regulations in April 2026 and Net Billing Regulations in June 2026 for grid-connected systems of 50 kWp to 1.5 MWp.

Regulations and grid connection

  • The Electricity Act 2023 allows states to set up their own electricity markets and regulators; NERC regulates until a state takes over.
  • Net Billing Regulations 2026: eligible customers with solar of 50 kWp to 1.5 MWp can export approved surplus; exports are credited at an export tariff (currently 0.55 off-peak and 0.75 peak factors), not one-for-one.
  • Mini-Grid Regulations 2026 set capacity thresholds, tariff rules, grid-arrival protocols and milestone reporting for mini-grid developers.
  • Most household systems are self-generation behind the meter; grid-interactive systems must be notified to the distribution company (DisCo).

Certifications

  • Imported products need SONCAP certification from the Standards Organisation of Nigeria; locally assembled products need MANCAP.
  • NEMSA type approval applies to inverters (IEC 62109), modules (IEC 61215 and IEC 61730) and batteries (IEC 62619 for lithium).
  • Rooftop installations must be carried out by NEMSA-certified electrical contractors, under NEMSA rooftop safety guidelines.

Incentives and funding

  • The Nigeria Customs Service confirmed in April 2024 that, under the ECOWAS Common External Tariff 2022–2027, there is no import duty or VAT on solar panels. Other components may still attract duties.
  • Net billing credits exported energy against import charges; credits carry forward.
  • Pioneer status can give qualifying manufacturers tax holidays of up to five years.

Installation rules

  • NEMSA-certified contractor, NEMSA-approved equipment, and earthing and surge protection suited to local lightning risk.
  • For net billing: DisCo feasibility report (15 business days), Net Billing Agreement, NERC registration, NEMSA inspection and DisCo commissioning before any export.

Compliance

  • Commercial and industrial solar that replaces diesel generation is the largest opportunity, often under lease or PPA models.
  • Mini-grids for unserved and underserved communities, supported by the Rural Electrification Agency and development finance.
  • Interconnected mini-grids with DisCos under NERC’s commercial framework guidelines.

What’s changing

  • 2026-04: NERC Mini-Grid Regulations 2026 replaced the 2023 regulations on 10 April 2026.
  • 2026-06: NERC Net Billing Regulations 2026 were released on 3 June 2026.

Official sources

Last verified 9 November 2026.